Skip to Main Content

General Service - Three Phase

 

AVAILABILITY

Available to consumers for all types of usage where the average monthly demand will not exceed 75 kW, subject to the established rules and regulations of the Cooperative.

TYPE OF SERVICE

Three phase, 60 cycles, at available secondary voltages.

MONTHLY RATE

Facility Charge................................................................ $77.50

Energy Charge:

First 2,000 kWh........................................................... $0.120 per kWh

Over 2,000 kWh.......................................................... $0.075 per kWh

MINIMUM CHARGES

The Cooperative shall determine the minimum monthly charge based on one of the following methods:

  1. The minimum monthly charge specified in the contract for service.
  2. A charge of $1.20 per kVA of required transformer capacity.
  3. The monthly facility charge, as shown above.

MINIMUM ANNUAL CHARGES

Unless otherwise stated in the contract for service, a consumer may guarantee a minimum annual charge, in which case, there shall be no minimum monthly charge.  The minimum charge shall be sufficient to assure adequate compensation for facilities installed to serve the load and, in no event, shall it be less than twelve times the minimum monthly charge determined in accordance with the foregoing paragraph.

PURCHASED POWER COST ADJUSTMENT CHARGE

The energy charge is subject to upward or downward adjustment to reflect variations in purchased power costs.

STATE AND MUNICIPAL TAXES

All applicable state and municipal sales tax and any other non-ad valorem taxes imposed on electric energy sales shall be applied to monthly bills rendered under this rate schedule unless the consumer is exempt from said tax or taxes.

TERMS OF PAYMENT

In the event the current monthly bill is not paid in accordance with the payment dates indicated on the bill, a late payment penalty in effect at the time shall apply.

This rate schedule supersedes rate schedule GS-3 adopted July 31, 2014.

EFFECTIVE DATE: May 2016 billing period

BOARD APPROVED: April 21, 2016