Available to commercial and industrial consumers providing their own transformation, subject to the established rules and regulations of the Cooperative.
Three phase, 60 hertz, 7200/12500 volts (nominal within standard industry practices).
Facility Charge.............................................................. $200.00
Demand Charge:
Coincidental Demand................................................ $25.00 per kW, plus
Maximum Demand..................................................... $5.00 per kW
Energy Charge................................................................... $0.041 per kWh
The minimum monthly charge shall be as specified in the agreement or contract for electric service.
1. The coincidental demand shall be equal to the customer's contribution to the monthly billing demand from the Cooperative's power supplier, East River Electric Power Cooperative.
2. The maximum demand shall be the maximum kilowatt demand established by the customer for any period of fifteen consecutive minutes during the month for which the bill is rendered, as indicated or recorded by a demand meter and adjusted for power factor.
The consumer agrees to maintain unity power factor as nearly as practicable. Demand charges may be adjusted to correct for average power factor lower than 90 percent, and may be so adjusted for other consumers if and when the Cooperative deems necessary. Such adjustment will be made by increasing the measured demand one percent for each one percent by which the average power factor is less than 90 percent lagging.
The demand and energy charge is subject to upward or downward adjustment to reflect variations in purchased power costs.
All applicable state and municipal sales tax and any other non-ad valorem taxes imposed on electric energy sales shall be applied to monthly bills rendered under this rate schedule unless the consumer is exempt from said tax or taxes.
In the event the current monthly bill is not paid in accordance with the payment dates indicated on the bill, a late payment penalty in effect at the time shall apply.
This rate schedule supersedes rate schedule PV-3 adopted April 21, 2016.
EFFECTIVE DATE: May 2017 billing period
BOARD APPROVED: March 23, 2017